Pleasant Valley Trail

Location: Laporte, CO

Contract Amount: $310,000

NCC Project Manager: Will Vickers

NCC Superintendent: Ed Strack

Quantity Highlights: Remove and replace bridge, mile of trail construction

Description: The project consisted of removing a bridge and installing a 16’x6’ Precast Concrete Box Culvert, and reconstructing mile of asphalt trail. The work was required to be completed in a ten day closure. The project included working around numerous underground utilities, as well as overhead electric.

No Comments Yet.